Making of Veja Mate Offshore Wind Farm

Comment

Making of Veja Mate Offshore Wind Farm

Veja Mate is pleased to present this short video which provides insight on how it completed construction in just 23 months after Financial Close.

All of its 67 turbines are now feeding green, renewable electricity into the German grid from the North Sea.

Comment

Veja Mate completes construction

Comment

Veja Mate completes construction

With the installation and commissioning of the last of its 67 Siemens SWT-6.0-154 turbines over the weekend, Veja Mate completed construction in less than 14 months and just 23 months after Financial Close (FC).

Comment

Veja Mate delivers first power from the North Sea

Comment

Veja Mate delivers first power from the North Sea

Veja Mate Offshore Wind Farm has reached an important milestone.  In just 18 months after financial close, the first Siemens 6MW wind turbine has started supplying the German electricity grid with green, renewable energy two months ahead of schedule.

Comment

Veja Mate Offshore Project Installs OSS

Comment

Veja Mate Offshore Project Installs OSS

Veja Mate Offshore Project is pleased to announce the installation of its Offshore Substation (OSS) delivered by FICG.  Just last week the OSS topside left Hoboken Belgium and sailed-away to Eemshaven where it was picked up a few days later by Heerema Marine Contractors (HMC). It joined the OSS jacket which had left Vlissingen Netherlands to arrive at the Veja Mate Offshore Site after a three-day journey.

Comment